A second new nuclear reactor is completed in Georgia. The carbon

opinions2024-05-21 15:09:234

ATLANTA (AP) — The second of two new nuclear reactors in Georgia has entered commercial operation, capping a project that cost billions more and took years longer than originally projected.

Georgia Power Co. and fellow owners announced the milestone Monday for Plant Vogtle’s Unit 4, which joins an earlier new reactor southeast of Augusta in splitting atoms to make carbon-free electricity.

Unit 3 began commercial operation last summer, joining two older reactors that have stood on the site for decades. They’re the first two nuclear reactors built in the United States in decades.

The new Vogtle reactors are currently projected to cost Georgia Power and three other owners $31 billion, according to calculations by The Associated Press. Add in $3.7 billion that original contractor Westinghouse paid Vogtle owners to walk away from construction, and the total nears $35 billion.

Address of this article:http://germany.fivesixgroup.com/article-73f899071.html

Popular

Hollywood star Shia LaBeouf is spotted on the streets of Gavin and Stacey's hometown Barry

I get shamed by other mothers for being naturally pretty with a good figure

Return to sender! Bizarre items that arrived in the post and left people terrified

Masterful meals: Masterchef 2010 champion Dhruv Baker's cherry and hazelnut chocolate roulade  

Election 2024: Biden and Trump bypassed the Commission on Presidential Debates

David de Gea jokingly asks 'who' as he responds to former Man United team

Australian pilot kidnapped in Papua New Guinea's highlands

JULIE BURCHILL: Why I spread rumours about Kate

LINKS